Cronología del cepillo de dientes eléctrico OEM: Guía del proceso semana a semana (2026)
Project timelines depend on product scope, tooling, approvals, testing, supplier readiness, freight, customs, and destination. Use the calendar below as a planning example, then confirm milestones against the project and current availability.

Resumen ejecutivo: Cronología de la producción de cepillos de dientes eléctricos OEM
- Cronología OEM estándar: 12–16 weeks (84–112 days) is an illustrative inquiry-to-delivery planning range, not a guaranteed lead time. Confirm the project schedule.
- An existing-platform ODM project may avoid some structural tooling if the model and configuration fit. MOQ, customization, setup charges, testing, and timing depend on the product and written terms.
- Principales riesgos de retraso: Schedule risks can include design changes, testing availability, supplier closures, component or packaging readiness, freight, and customs. Set project-specific buffers and confirm dates with the relevant providers.
- Payment and tooling milestones are negotiated contract terms. Specify deposits, balance triggers, tooling ownership, acceptance conditions, and nonconformity handling in the signed agreement.
En esta guía
- Cronología completa de un vistazo
- Fase 1: Investigación y selección de fábrica (Semanas 1-2)
- Fase 2: Desarrollo de muestras y prototipos (Semanas 3-8)
- Fase 3: Producción en serie (Semanas 9-12)
- Fase 4: Envío y despacho de aduanas (Semanas 13-16)
- Existing-platform ODM options
- Principales riesgos de retraso y cómo prevenirlos
- Planificación inversa del calendario: Trabaje hacia atrás desde su fecha de lanzamiento
- Preguntas frecuentes
1. Cronología completa de un vistazo
Antes de entrar en cada una de las semanas, he aquí el cuadro completo. Conocer la forma general del calendario te ayudará a negociar con las fábricas, fijar fechas de lanzamiento realistas y determinar dónde es más importante el tiempo de amortiguación.

🏭 Acerca del fabricante: Relish Technology
Relish Technology has manufactured oral-care products since 2012. Its operations in Shenzhen and Huizhou total 20,000 m². Share the product configuration, target market, order scope, and schedule to discuss relevant manufacturing options and product-specific documentation.
Más información → · Estudios de casos de clientes → · Ver certificaciones →
OEM Electric Toothbrush: Illustrative 16-Week Timeline (Visual Overview)
| Fase | Semanas | Actividades principales | Sus puntos de decisión |
|---|---|---|---|
| 1. Consulta y selección | 1–2 | RFQ, comparación de presupuestos, firma de NDA, preselección en fábrica | Elegir fábrica, confirmar especificaciones |
| 2. Creación de moldes | 3–6 | Revisión de ingeniería, fabricación del molde, primera prueba del molde | Aprobación del diseño del molde, pago del depósito de utillaje |
| 3. Prototipo y aprobación | 7–8 | Primeras muestras, pruebas, revisiones, aprobación previa a la producción | Aprobación de muestras, firma de la orden de compra |
| 4. Producción en serie | 9–12 | Production deposit, inline checks, packaging, and pre-shipment inspection: schedule and payment terms are project-specific and contractual. | Review inspection results and follow the payment terms agreed in the contract. |
| 5. Envío y liquidación | 13–16 | Flete marítimo/aéreo, agente de aduanas, entrega de última milla | Confirmar la recepción, registrar el inventario |
Un número para recordar
Use the 16-week calendar as an example, then build a project-specific schedule. Add time for design changes, sample review, testing, transport, and clearance after confirming requirements with each supplier or service provider.
2. Fase 1 - Investigación y selección de fábrica (Semanas 1-2)
Early supplier evaluation helps clarify product scope, documentation, commercial terms, and schedule assumptions before tooling or production begins.

Preparación de peticiones de oferta y difusión multifactoría
ConsultaEmpieza la primera semana escribiendo un Solicitud de presupuesto (RFQ) y enviarla simultáneamente a 4-6 fábricas. La calidad de la petición de oferta determina la calidad de los presupuestos que recibirá. Las solicitudes imprecisas obtienen respuestas imprecisas y precios inflados que no se hacen evidentes hasta más tarde.
- Define product specifications: Drive technology and specified motion metric, battery voltage and capacity/Wh, applicable ingress-protection target, handle dimensions, brush-head type, charging method, and operating modes.
- Establezca sus cantidades objetivo: Indique la cantidad de su pedido inicial y el volumen anual previsto. Las fábricas fijan precios diferentes para 500 y 5.000 unidades
- List destination-market compliance requirements: identify applicable product rules and evidence for the model and configuration; confirm testing and documentation with the laboratory or qualified adviser.
- Especifique los requisitos de embalaje: Dimensiones de la caja minorista, tarjeta de inserción, caja principal, requisitos de etiquetado Amazon-ready
- Identificar 4-6 fábricas candidatas: Utilice los directorios de la Feria de Cantón, el filtro de proveedores de oro de Alibaba, Made-in-China.com o referencias directas.
Una petición de oferta completa abarca estos ocho puntos
Nombre del producto y una descripción de 1-2 líneas. Una hoja de especificaciones técnicas con dimensiones, materiales y objetivos de rendimiento. Su mercado o mercados objetivo y las certificaciones necesarias. Cantidad del pedido inicial y previsión de volumen a 12 meses. Especificaciones de embalaje, tanto para la venta al por menor como para la caja principal. Cantidad de muestras y plazos de entrega. Rango de precios FOB objetivo: es opcional, pero ayuda a filtrar las fábricas que no son competitivas en su rango. Y las condiciones de pago previstas.
Evaluación de ofertas y selección de fábrica
SelecciónCompare quotations on identical specifications, quantity, Incoterms, testing, packaging, and documentation. Assess total landed cost and assumptions; price alone does not establish supplier quality or future rework cost.
- Compare presupuestos sobre la misma base: Confirme que todos los presupuestos utilizan los mismos Incoterms (normalmente FOB Shenzhen), incluyen las mismas certificaciones y cubren idénticas especificaciones de embalaje.
- Verify the supplier: Check its business registration and any claimed ISO 9001 certificate. For comparable products, request model-specific test reports and conformity documents relevant to your target market. CE is a conformity mark; FCC requirements depend on the product configuration.
- Evalúe la velocidad de comunicación: Track response times during evaluation and agree on communication expectations and escalation contacts before production.
- Solicitar perfil de fábrica: ¿Cuántas líneas de producción? ¿Capacidad anual? Principales clientes actuales (anónimos) ¿Han exportado antes a su mercado objetivo?
- Shortlist suppliers for further review. If needed, commission a scoped factory audit and obtain a current quotation from the provider.
Cómo es una fábrica fiable
A supplier should explain its capabilities, identify open technical questions, provide current documentation for comparable products, and agree on a practical communication and review process. Verify claims against the project scope.
Aléjate si ves esto
Investigate inconsistent quotations, unclear documentation, or pressure to skip written terms. Compare like-for-like costs and seek clarification; no single signal proves fraud.
3. Fase 2 - Desarrollo de muestras y prototipos (Semanas 3-8)
Sample development may take several weeks and require review rounds. Consolidate feedback, document approved changes, and evaluate new requirements against the schedule.

Revisión de ingeniería y confirmación del diseño del molde
Lanzamiento de herramientasAfter scope and commercial terms are agreed, engineering reviews design, tooling, materials, assembly, and available processes. The number of questions and response time depend on the project.
- DFM review: Ask engineering to identify design, tooling, assembly, and process questions and document any proposed changes.
- Review proposed CAD and tooling designs before authorizing fabrication. Changes after work begins may affect engineering, time, and cost; define approval and tooling ownership in writing.
- Confirmación de material: Confirme el material del mango (ABS / PC / mezcla de ABS+PC), el material de las cerdas (nylon / DuPont Tynex) y las especificaciones del sobremoldeado de TPE/caucho.
- Document the relevant vibration or brush-head movement metric and test method; distinguish VPM, Hz, and rotational speed. Do not call sonic operation ultrasonic without supporting frequency data.
- Tooling cost and payment timing depend on design and contract. Agree amount, ownership, acceptance milestone, and payment triggers in writing.
Fabricación de moldes (mecanizado CNC)
HerramientasDuring mold fabrication, request updates at agreed milestones. Toolmaking requires inspection and adjustment; the appropriate correction depends on the issue and engineering assessment.
- Tooling lead time and durability depend on design, material, process, workload, production conditions, and maintenance. Obtain a project-specific estimate.
- Solicite fotos del progreso: Solicite fotos de mecanizado CNC en la terminación 50% y 100%
- Tareas paralelas durante esta espera:
- Finalizar el logotipo de la marca y la paleta de colores para la textura del molde
- Borrador del diseño del envase de venta al por menor para su revisión en fábrica
- Ask your testing lab to review the rules and test scope for the intended product and destination markets.
- Prepare importer-of-record arrangements if required for the destination and transaction.
- Tool life depends on grade, heat treatment, mold design, resin, production conditions, and maintenance; quoted shot counts are not universal guarantees.
No pierda las Semanas 4-5 esperando
Use the mold fabrication period to finalize packaging design and send it to the factory for a mockup. Register barcodes (EAN/UPC) for each SKU early enough to support listing and packaging preparation. Prepare listing copy, warehouse arrangements, and draft manuals while tooling is underway. Review regulatory requirements with the laboratory early; product testing and final approvals may need representative samples.
Primera prueba de moho y muestras T1
Primeros disparosA first mold trial (often called T1) evaluates molded parts and fit. It may identify dimensional, surface, or assembly issues and is not necessarily a complete functional product.
- Inspección dimensional T1: La fábrica mide las dimensiones críticas comparándolas con los planos aprobados mediante MMC (máquina de medición por coordenadas) o calibres.
- Revisión del acabado superficial: Compruebe la textura, el nivel de brillo, la visibilidad de la línea de separación y cualquier marca de hundimiento o línea de soldadura.
- Ensayo de la asamblea: Las mitades de la carcasa se ensamblan con los componentes internos (PCB, motor, batería) para comprobar el ajuste y el apilamiento de tolerancias.
- T1 findings and corrective actions:
- Inspect flash, sink marks, weld lines, fit, and surface texture against the drawing and sample criteria.
- Ask engineering to identify root cause before approving a design, process, or tooling change.
- Record corrective actions and re-trial timing in the project schedule; no single repair or turnaround applies to every case.
- Review the updated sample before approving the next stage.
- Solicite el envío físico de muestras T1: Incluso con fotos, la evaluación práctica revela cosas que una cámara pasa por alto. Calidad táctil, distribución del peso, sensación de los botones

Muestra de preproducción (prototipo funcional) y pruebas
Pruebas por muestreoThe pre-production sample should represent the agreed design closely enough for review. Define tests, sample size, conditions, acceptance criteria, and any changes requiring reassessment.
- Functional sample testing:
- Battery runtime: Define sample, charge state, operating mode, load, and stop criteria. One condition does not establish runtime for every mode or battery.
- IPX7 immersion: Use applicable IEC 60529 conditions, commonly 1 m for 30 minutes for the relevant enclosure. Longer duration is not an IPX7 requirement; an air-pressure screen is not the water test.
- Prueba de caída: Agree sample, height, surface, orientations, repetitions, and pass criteria in the project protocol.
- Brush-head attachment: Define sample, cycle count, and evaluation criteria in the product specification.
- Charging/cycle test: Specify charger, battery, cycle count, measurements, and acceptance criteria.
- Vibration measurement: Document instrument, measurement point, method, and metric; distinguish sonic vibration from ultrasonic frequency and rotational speed.
- Temperature test: Define product state, exposure duration, operating condition, and criteria; limited testing does not prove all-environment performance.
- Revisión del prototipo de envase: Compruebe los colores impresos de la caja de venta al por menor (solicite una prueba exacta de Pantone), la posibilidad de escanear el código de barras y el ajuste de la tarjeta de inserción.
- User manual review: Check labeling and instructions against the requirements applicable to each destination market and product configuration.
Antes de dar el visto bueno a la muestra de preproducción
Compare the production-representative sample and documented results against the agreed specifications and criteria. Determine whether changes require further testing or approval before production.
Confirmación de pedidos y programación de la producción
Inicio de la producción en serieAfter sample and commercial terms are approved, issue a purchase order and confirm the production slot. Define specifications, quantity, price, delivery terms, inspection criteria, and payment schedule in writing.
- Emitir una orden de pedido formal: El pedido firmado debe especificar las cantidades exactas por referencia, el precio unitario, los Incoterms, el plazo de entrega, las especificaciones de embalaje y las condiciones de pago.
- Confirmación del calendario de producción: La fábrica proporciona un diagrama de Gantt o un programa de producción que muestra la fecha de inicio, la finalización estimada y los hitos de control de calidad.
- Component procurement: Confirm availability and lead times for specified PCBs, batteries, motors, and materials with the supplier; update the project schedule if an item is not ready.
- Packaging production kickoff: Coordinate artwork approval, production quantity, and delivery timing with the packaging supplier and assembly schedule.
- Inspection planning: Agree the inspection scope, provider, sample plan, and timing with the supplier and inspector; availability varies.
4. Fase 3 - Producción en serie (Semanas 9-12)
Agree on status updates and records to be shared. Use documented progress, inspection results, and issue tracking; follow the supplier agreement and site rules.

Producción activa y control de calidad en línea
ProducciónDocument production checkpoints, test coverage, sample plans, limits, and failure handling against the approved specification.
- Inline quality checkpoints (document the agreed plan):
- Housing: check dimensions and visible defects against the approved specification and sampling plan.
- PCB: document test coverage and limits; describe a check as 100% only if each unit receives the stated test.
- Assembly: verify alignment and seals against the specification. An air-pressure screen is not an IEC 60529 water-ingress test.
- Final function: identify the functions tested per unit and how failures are recorded and handled.
- Packaging: verify SKU, labels, accessories, and carton data against the approved specification.
- Solicite fotos/vídeos semanales de la producción: Unidades terminadas en la línea, registros de inspección de control de calidad y línea de envasado en funcionamiento
- Siga el progreso de la producción: For example, compare reported output with the production schedule and order quantity; investigate material variances early.
- If testing is required, confirm representative samples, scope, lab schedule, and production-change implications with the lab; timing is not guaranteed.
Señales de alarma a mitad de producción: actúe de inmediato
If the factory goes quiet without explanation, something is wrong. If they suddenly ask to substitute a component because of "stock issues," push back—get the original spec or a written explanation. If production pace falls significantly behind schedule with no clear reason, escalate. If a supplier requests payment ahead of an agreed milestone, compare the request with the contract and resolve any discrepancy in writing before payment.

Finalización de la producción e inspección previa al envío
Control de calidad e inspecciónPre-shipment inspection can check goods against the agreed purchase order and acceptance plan. Define scope and process in advance; it does not guarantee every shipped unit.
- Alcance de la inspección previa al envío:
- Quantity: compare physical count with the PO and any tolerance expressly agreed in contract.
- Sampling: specify procedure, inspection level, sample size, defect classes, and acceptance/rejection numbers. AQL is a plan parameter, not measured defect rate; MIL-STD-1916 uses verification levels, not an AQL table.
- Workmanship: assess surface, color, assembly, and agreed criteria.
- Function: identify test functions, sample plan, and pass criteria.
- Packaging: verify carton markings, accessories, and barcodes against the approved specification.
- Carton drop testing: use the agreed protocol for height, orientations, surface, repetitions, and acceptance criteria.
- Choose an independent provider, buyer-appointed representative, or supplier records based on the agreed scope and evidence requirements. Fees and availability vary; confirm in writing.
- Document the nonconformity, corrective action, rework, and re-inspection criteria. Added time depends on the issue and agreed disposition.
- Prepare documents according to route, product, battery configuration, destination, and buyer requirements. Use a certificate of origin or conformity document only when applicable.
Criterios de aprobación de la inspección previa a la expedición
Use the quantity, sampling plan, function checks, packaging, markings, and documents in the contract. If results miss criteria, document corrective action and verify closure before shipment.
5. Fase 4 - Envío y despacho de aduanas (Semanas 13-16)
Shipping and customs timing depends on route, carrier, service, documents, battery configuration, port conditions, and clearance. Treat the week numbers as illustrative and confirm the current plan.

Recogida de carga y aduanas de exportación (China)
SalidaThe forwarder coordinates pickup and export formalities. Clearance timing depends on the shipment and its documents; confirm cutoffs and required records for the chosen service.
- Sea freight planning examples:
- Shenzhen to Los Angeles: request a current route and service estimate.
- Shenzhen to Hamburg or Rotterdam: request a current route and service estimate.
- Shenzhen to Tokyo or Osaka: request a current route and service estimate.
- Shenzhen to Sydney: request a current route and service estimate.
- Air freight may suit samples or urgent shipments. Transit and cost depend on route, service, chargeable weight, battery acceptance, and current capacity; compare current quotes.
- Classification depends on product configuration, jurisdiction, origin, and import date. Treat HS 8509.80 only as a possible heading to investigate, not a final national tariff code or duty.
- Shipment document checklist (confirm what applies):
- Commercial invoice with accurate transaction value and required shipment information.
- Packing list with package count, weights, dimensions, and contents as required.
- Bill of Lading or Air Waybill for the selected service.
- Certificate of origin only if required by destination, buyer, or applicable procedure; confirm correct form and origin rules.
- Applicable conformity documentation for the product and destination.
- FCC documentation only when applicable to the product and import.
- Battery test summary and shipping information required for the battery design and shipment mode.
Crítica: Cumplimiento de la normativa sobre transporte de baterías de litio
For lithium-battery products, identify battery type, watt-hours, packing configuration, shipment mode, and applicable rules. Obtain the required UN 38.3 test summary and confirm declarations and labels for that shipment; air and sea rules differ.
Preparación aduanera para el tránsito y la importación
TránsitoPrepare import paperwork before arrival. Confirm free time, storage or demurrage terms, and broker deadlines from current carrier and port information; charges vary.
- Share documents according to the broker’s agreed lead time. Pre-arrival review can identify gaps; no fixed number of days applies to every shipment.
- For applicable U.S. vessel shipments, determine whether ISF applies and submit required information within the regulatory timeframe before loading. ISF is not a general air-freight filing.
- For EU imports, confirm the economic operator and importer arrangements, applicable conformity documents, and customs registration requirements with the importer and broker. Keep these separate from the rules for Great Britain and Northern Ireland.
- Confirm the conformity route for Great Britain or Northern Ireland and the product. Great Britain recognizes CE alongside UKCA for many applicable products under current arrangements; Northern Ireland differs.
- Aranceles de importación a tener en cuenta:
- US: duty and additional tariffs depend on final classification, origin, product details, and import date. Check current official sources and obtain broker advice.
- EU: determine duty from the final classification, origin, and import date; do not rely on a generic percentage.
- UK: determine duty from the final commodity code, origin, and import date.
- Prepare fulfillment requirements before dispatch. For Amazon FBA, confirm current carton, labeling, prep, and shipment-plan requirements in Seller Central; these differ from standard third-party logistics.
Entrega, recepción y puesta en marcha del inventario
LlegadaLa carga pasa el control de aduanas y se entrega en su almacén o centro de distribución. El proyecto OEM está terminado. Pero el trabajo no ha terminado. La recepción es un punto de control de calidad que muchas marcas se saltan en detrimento suyo.
- Reconcile carton count and visible condition, then inspect units under the receiving plan agreed for the order. Any percentage sample is project-specific, not universal.
- Actualización del sistema de inventario: Registre los números de lote, las fechas de producción y los códigos de lote. Esto es importante para las reclamaciones de garantía y las posibles retiradas de productos.
- Amazon FBA receiving (if applicable): Reconcile delivered cartons and monitor receiving status against the shipment plan created before dispatch. Inventory availability depends on Amazon's processing.
- Fotografía y actualización de listados: Si aún no dispone de fotografías de productos, organice inmediatamente una sesión fotográfica en su empresa o en un estudio. Desea que los anuncios se publiquen a los pocos días de que el inventario esté disponible.
- Informe del proyecto: Documente lo que ha ido bien, lo que ha causado retrasos y lo que haría de otro modo. Esto se convierte en el procedimiento normalizado de fabricación para la siguiente producción.
¿Está listo para iniciar su proyecto de cepillo de dientes eléctrico OEM?
Share your project brief to discuss a quotation and schedule. Scope, MOQ, tooling, testing, sample terms, and current capacity depend on the product and written agreement.
¿Cuál es su fecha de lanzamiento? Inclúyala en el formulario: le diremos si el plazo es realista.
6. Existing-Platform ODM Options
ODM may suit a project that fits an existing platform and available configuration. New tooling may still be needed for structural changes; branding, accessories, packaging, testing, and schedule depend on the agreed scope. Compare total cost, MOQ, rights, and timing with an OEM proposal.
Custom OEM: A project-specific design may involve engineering and structural tooling. Confirm timeline, tooling charges, MOQ, design scope, and intellectual-property rights in the written agreement.

Existing-platform ODM: An existing platform may reduce some development or tooling work if it fits the brief. Confirm customization limits, setup charges, MOQ, testing, schedule, and intellectual-property rights in the written agreement.
Illustrative ODM Milestones
The sequence below shows how work may progress on an existing platform; confirm sample, production, freight, and receiving dates for the actual project.
| Semana | Actividad | Acciones clave para usted |
|---|---|---|
| Semana 1 | Browse existing-platform options, if available, and request project-specific samples. | Review product fit, configuration, sample terms, MOQ, and schedule. |
| Semana 2 | Recepción de unidades de muestra; comprobación de la funcionalidad; confirmación de la selección | Aprobar el modelo de producto |
| Semana 3 | Presentar la marca: logotipo, colores, diseño de envases | Proporcionar activos de marca completos |
| Semana 4 | La fábrica prepara muestras de preproducción personalizadas | Revisión y aprobación de la muestra |
| Semana 5 | Issue the purchase order and follow the written payment terms. | Emisión PO |
| Semanas 6-8 | Producción en serie, control de calidad en línea, envasado | Supervisar los progresos, registrar la ISP |
| Semana 9 | Review inspection results and follow the agreed payment and shipping terms. | Aprobar la inspección, organizar el transporte |
| Semana 10 | Despacho de aduanas, entrega | Recibir inventario, activar listados |
Cuando ODM gana a OEM
ODM may suit a project that fits an existing platform. Compare MOQ, customization, tooling or setup charges, testing, schedule, IP terms, and total cost with an OEM proposal; confirm any trial quantity in writing.
7. Dónde se rompen realmente los plazos de los OEM
The following factors can affect a project schedule; assess them against the supplier plan and current service estimates.

Mold revisions and design changes
Review design and tooling changes before fabrication. Record approval, cost, and schedule impact in the project plan.
Atrasos en los laboratorios de certificación: invisibles hasta que se atascan
Laboratory availability varies by product, test scope, market, season, and provider. Confirm current availability and whether representative samples can be evaluated.
Año Nuevo chino: los trastornos que se ven venir a 12 meses vista
Chinese New Year dates and supplier closures vary by year and factory. Check the official calendar and obtain planned closure and restart dates from each supplier; use a project-specific buffer.
Envases y productos que llegan en momentos diferentes
Packaging may come from a separate supplier. Coordinate artwork, quantity, production, and delivery dates with the packaging supplier.
Ejemplos de bucles de revisión: retroalimentación continua
Revision rounds can extend sample approval. Consolidate feedback in one document, rank issues, and confirm the schedule impact of each approved change.
Escasez de componentes: el problema de la cadena de suministro que aflora a mitad de la producción
Components such as PCBs and batteries can affect timing if supply is not confirmed. Ask the supplier to document availability and proposed alternatives; assess any substitution through change control. A second source may help where technically and contractually feasible.
Retrasos marítimos y portuarios: la última milla que suma semanas
Freight schedules vary with routing, capacity, port conditions, documents, and customs. Use current estimates and allow a project-specific buffer.
Keep milestones and decisions visible
Agree on a regular update cadence and document milestones, open issues, and decisions. Follow up on unexplained communication gaps and assess their effect on the project schedule.
8. Planificación inversa del calendario: Trabaje hacia atrás desde la fecha de lanzamiento
Reverse-calendar planning can clarify dependencies. Work backward from a target availability date using supplier, testing, production, freight, customs, and warehouse estimates confirmed for the project.

Ejemplo: Planificación del lanzamiento de Amazon en el cuarto trimestre de la temporada navideña
Illustrative target only: confirm current event eligibility, FBA appointments, receiving requirements, and the actual transit plan; this is not an official deadline.
| Hito | Fecha objetivo | Notas |
|---|---|---|
| Productos recibidos en el almacén FBA | 1 de octubre | Allow for current FBA appointment, receiving, and processing times; these vary and are not a fixed 1–2-week guarantee. |
| Despacho de aduanas + entrega en la última milla | 25 de septiembre | Illustrative only; confirm port, clearance, and last-mile timing for the route. |
| Envío desde Shenzhen (flete marítimo) | 28 de agosto | Illustrative port-to-port estimate only; confirm current route, service, and door-to-door timing with the forwarder. |
| Inspección previa al envío superada | 21 de agosto | Allow time for inspection and documents according to the agreed scope and route. |
| Producción en serie completa | 14 de agosto | Illustrative production window; confirm current capacity and schedule. |
| Purchase Order issued / payment milestone per contract | 17 de julio | Inicio de la producción en serie |
| Muestra de preproducción aprobada | 10 de julio | Allow for sample review and applicable testing; confirm scope and laboratory schedule. |
| Muestras de moho T1 recibidas | 26 de junio | Review time depends on findings, corrective work, and approval. |
| Inicio de la fabricación de moldes | 5 de junio | Illustrative tooling window; request a project-specific estimate. |
| Fábrica seleccionada, contrato firmado | 29 de mayo | NDA, diseño de molde aprobado |
| Iniciar la difusión de las peticiones de oferta | 22 de mayo | Inicie aquí la búsqueda de fábrica |
Para un lanzamiento de Amazon FBA el 1 de octubre: Comience su búsqueda de fábrica antes del 22 de mayo
May 22 to October 1 is 132 days, about 18 weeks and 6 days in this example. This is a planning window, not a promise; update dates as milestones are confirmed.
Si te perdiste la ventana de mayo: compare a suitable existing-platform ODM option or revise the launch target. Actual timing and seasonal demand depend on the project and market.
Guía de horarios de temporada alta

| Ventana de lanzamiento del objetivo | Illustrative OEM Start Date | Illustrative ODM Start Date | Notas |
|---|---|---|---|
| Enero (Año Nuevo) | 1 de septiembre | 15 de octubre | Check the official calendar and obtain supplier closure and restart dates for the relevant year. |
| Febrero (San Valentín) | 15 de octubre | 1 de diciembre | Illustrative note only; confirm the official holiday calendar and each supplier’s closure and restart dates. |
| Abril (primavera) | 1 de diciembre | 15 de enero | Confirm supplier availability and restart dates for the relevant year. |
| Julio (Prime Day) | 1 de marzo | 15 de abril | Illustrative example only; verify current supplier and logistics availability. |
| Octubre (Pre-vacacional) | 22 de mayo | 15 de julio | Illustrative channel note; verify current market conditions. |
| Noviembre (Black Friday) | 15 de junio | 1 de agosto | Confirm current event-specific eligibility and submission dates; no universal October 15 cutoff is asserted. |
📚 Referencias

9. Preguntas frecuentes
Obtenga un calendario OEM personalizado para su proyecto
Tell us your target launch date and product requirements. Our project team can discuss a project-specific schedule and applicable commercial terms.
Tip: Include your target launch date, destination market, and product requirements so the schedule discussion can account for project constraints.

Siga investigando sobre OEM
- La guía completa para la fabricación de cepillos de dientes eléctricos OEM/ODM (2026): Resumen completo de costes, certificaciones, control de calidad, selección de fábricas
- OEM vs ODM vs OBM: ¿Qué modelo de fabricación es el adecuado para su marca?: Marco de decisión con comparaciones de costes reales
- Cómo encontrar un fabricante OEM en China: 6 métodos probados: Feria de Cantón, Alibaba, auditorías de fábricas y diligencia debida
- CE, FCC, PSE y más: La guía completa de certificación para cepillos de dientes eléctricos: Todas las certificaciones que necesita, por mercado
- Guía de la marca de distribuidor: Del logotipo al lanzamiento: Diseño de envases, identidad de marca y estrategia de lanzamiento al mercado
- Guía del comprador OEM/ODM de filtros de agua: ¿Quiere ampliar su línea de productos de cuidado bucal? Empiece aquí