Timeline degli spazzolini elettrici OEM: Guida al processo settimana per settimana (2026)
Project timelines depend on product scope, tooling, approvals, testing, supplier readiness, freight, customs, and destination. Use the calendar below as a planning example, then confirm milestones against the project and current availability.

Riepilogo esecutivo: Tempistica di produzione dello spazzolino elettrico OEM
- Tempistica OEM standard: 12–16 weeks (84–112 days) is an illustrative inquiry-to-delivery planning range, not a guaranteed lead time. Confirm the project schedule.
- An existing-platform ODM project may avoid some structural tooling if the model and configuration fit. MOQ, customization, setup charges, testing, and timing depend on the product and written terms.
- Principali rischi di ritardo: Schedule risks can include design changes, testing availability, supplier closures, component or packaging readiness, freight, and customs. Set project-specific buffers and confirm dates with the relevant providers.
- Payment and tooling milestones are negotiated contract terms. Specify deposits, balance triggers, tooling ownership, acceptance conditions, and nonconformity handling in the signed agreement.
In questa guida
- Panoramica completa della tempistica
- Fase 1: Richiesta e selezione della fabbrica (settimane 1–2)
- Fase 2: Sviluppo del campione e del prototipo (settimane 3–8)
- Fase 3: Produzione di massa (settimane 9–12)
- Fase 4: Spedizione e sdoganamento (settimane 13–16)
- Existing-platform ODM options
- Principali rischi di ritardo e come prevenirli
- Pianificazione a calendario inverso: lavorare a ritroso dalla data di lancio
- Domande frequenti
Panoramica completa della tempistica
Prima di addentrarci nelle singole settimane, ecco il quadro completo. Conoscere la forma generale della tempistica aiuta a negoziare con le fabbriche, stabilire date di lancio realistiche e capire dove il tempo buffer è più importante.

🏭 Informazioni sul produttore: Relish Technology
Relish Technology has manufactured oral-care products since 2012. Its operations in Shenzhen and Huizhou total 20,000 m². Share the product configuration, target market, order scope, and schedule to discuss relevant manufacturing options and product-specific documentation.
Per saperne di più → · Casi di studio dei clienti → · Visualizza le certificazioni →
OEM Electric Toothbrush: Illustrative 16-Week Timeline (Visual Overview)
| Fase | Settimane | Attività Chiave | I Tuoi Punti Decisionali |
|---|---|---|---|
| Richiesta & Selezione | 1–2 | RFQ, confronto preventivi, firma NDA, shortlist fabbriche | Scegli fabbrica, conferma specifiche |
| Creazione Stampi | 3–6 | Revisione ingegneristica, fabbricazione stampo, primo test stampo | Approva design stampo, paga acconto attrezzatura |
| Prototipo & Approvazione | 7–8 | Primi campioni, test, revisioni, approvazione pre-produzione | Approva campioni, firma ordine d'acquisto |
| 4. Produzione di massa | 9–12 | Production deposit, inline checks, packaging, and pre-shipment inspection: schedule and payment terms are project-specific and contractual. | Review inspection results and follow the payment terms agreed in the contract. |
| Spedizione & Sdoganamento | 13–16 | Trasporto marittimo/aereo, broker doganale, consegna ultimo miglio | Conferma ricevimento, registra inventario |
Un Numero da Ricordare
Use the 16-week calendar as an example, then build a project-specific schedule. Add time for design changes, sample review, testing, transport, and clearance after confirming requirements with each supplier or service provider.
Fase 1 — Richiesta & Selezione Fabbrica (Settimane 1–2)
Early supplier evaluation helps clarify product scope, documentation, commercial terms, and schedule assumptions before tooling or production begins.

Preparazione RFQ & Contatto Multi-Fabbrica
RichiestaInizia la Settimana 1 scrivendo una chiara e dettagliata Richiesta di Quotazione (RFQ) e inviandola a 4-6 fabbriche simultaneamente. La qualità del tuo RFQ determina la qualità dei preventivi che riceverai. Richieste vaghe ottengono risposte vaghe—e prezzi gonfiati che non sono evidenti fino a dopo.
- Define product specifications: Drive technology and specified motion metric, battery voltage and capacity/Wh, applicable ingress-protection target, handle dimensions, brush-head type, charging method, and operating modes.
- Imposta le quantità target: Indica la quantità dell'ordine iniziale e il volume annuale previsto. Le fabbriche prezzano diversamente per 500 vs. 5.000 unità
- List destination-market compliance requirements: identify applicable product rules and evidence for the model and configuration; confirm testing and documentation with the laboratory or qualified adviser.
- Specifica i requisiti di imballaggio: Dimensioni scatola retail, inserto cartaceo, cartone master, requisiti etichettatura pronta per Amazon
- Identifica 4–6 fabbriche candidate: Usa directory Fiera di Canton, filtro Alibaba Gold Supplier, Made-in-China.com o referenze dirette
Un RFQ completo copre questi otto punti
Nome prodotto e descrizione di 1-2 righe. Una scheda tecnica con dimensioni, materiali e obiettivi di performance. I tuoi mercati target e certificazioni richieste. Quantità ordine iniziale più una previsione volume a 12 mesi. Specifica imballaggio sia per retail che per cartone master. Quantità campioni e requisiti tempi di consegna. Fascia di prezzo FOB target—questo è opzionale ma aiuta a filtrare fabbriche non competitive nella tua fascia. E i termini di pagamento previsti.
Valutazione Preventivi & Selezione Fabbrica
SelezioneCompare quotations on identical specifications, quantity, Incoterms, testing, packaging, and documentation. Assess total landed cost and assumptions; price alone does not establish supplier quality or future rework cost.
- Confronta i preventivi sulla stessa base: Conferma che tutti i preventivi utilizzino gli stessi Incoterms (tipicamente FOB Shenzhen), includano le stesse certificazioni e coprano specifiche di imballaggio identiche
- Verify the supplier: Check its business registration and any claimed ISO 9001 certificate. For comparable products, request model-specific test reports and conformity documents relevant to your target market. CE is a conformity mark; FCC requirements depend on the product configuration.
- Valuta la velocità di comunicazione: Track response times during evaluation and agree on communication expectations and escalation contacts before production.
- Richiedi il profilo della fabbrica: Quante linee di produzione? Capacità annuale? Principali clienti attuali (anonimizzati)? Hanno già esportato nel tuo mercato di destinazione?
- Shortlist suppliers for further review. If needed, commission a scoped factory audit and obtain a current quotation from the provider.
Come appare una fabbrica affidabile
A supplier should explain its capabilities, identify open technical questions, provide current documentation for comparable products, and agree on a practical communication and review process. Verify claims against the project scope.
Allontanati se vedi questo
Investigate inconsistent quotations, unclear documentation, or pressure to skip written terms. Compare like-for-like costs and seek clarification; no single signal proves fraud.
Fase 2 — Sviluppo Campione e Prototipo (Settimane 3–8)
Sample development may take several weeks and require review rounds. Consolidate feedback, document approved changes, and evaluate new requirements against the schedule.

Revisione Ingegneristica e Conferma del Design dello Stampo
Avvio AttrezzaturaAfter scope and commercial terms are agreed, engineering reviews design, tooling, materials, assembly, and available processes. The number of questions and response time depend on the project.
- DFM review: Ask engineering to identify design, tooling, assembly, and process questions and document any proposed changes.
- Review proposed CAD and tooling designs before authorizing fabrication. Changes after work begins may affect engineering, time, and cost; define approval and tooling ownership in writing.
- Conferma materiali: Conferma materiale del manico (ABS / PC / miscela ABS+PC), materiale delle setole (grado nylon / DuPont Tynex) e specifiche del sovrastampo in TPE/gomma
- Document the relevant vibration or brush-head movement metric and test method; distinguish VPM, Hz, and rotational speed. Do not call sonic operation ultrasonic without supporting frequency data.
- Tooling cost and payment timing depend on design and contract. Agree amount, ownership, acceptance milestone, and payment triggers in writing.
Fabbricazione dello Stampo (Lavorazione CNC)
AttrezzaturaDuring mold fabrication, request updates at agreed milestones. Toolmaking requires inspection and adjustment; the appropriate correction depends on the issue and engineering assessment.
- Tooling lead time and durability depend on design, material, process, workload, production conditions, and maintenance. Obtain a project-specific estimate.
- Richiedi foto di avanzamento: Chiedi foto della lavorazione CNC al 50% e al 100% di completamento
- Attività parallele durante questa attesa:
- Finalizzare il logo del marchio e la palette cromatica per la texture dello stampo
- Bozza del design della confezione retail per la revisione in fabbrica
- Ask your testing lab to review the rules and test scope for the intended product and destination markets.
- Prepare importer-of-record arrangements if required for the destination and transaction.
- Tool life depends on grade, heat treatment, mold design, resin, production conditions, and maintenance; quoted shot counts are not universal guarantees.
Non sprecare le settimane 4-5 aspettando
Use the mold fabrication period to finalize packaging design and send it to the factory for a mockup. Register barcodes (EAN/UPC) for each SKU early enough to support listing and packaging preparation. Prepare listing copy, warehouse arrangements, and draft manuals while tooling is underway. Review regulatory requirements with the laboratory early; product testing and final approvals may need representative samples.
Prima Prova dello Stampo e Campioni T1
Prime StampateA first mold trial (often called T1) evaluates molded parts and fit. It may identify dimensional, surface, or assembly issues and is not necessarily a complete functional product.
- Ispezione dimensionale T1: La fabbrica misura le dimensioni critiche rispetto ai tuoi disegni approvati utilizzando CMM (Macchina di Misura a Coordinate) o calibri
- Revisione della finitura superficiale: Controlla texture, livello di lucentezza, visibilità della linea di divisione ed eventuali segni di avvallamento o linee di saldatura
- Prova di assemblaggio: Le metà dell'alloggiamento vengono assemblate con i componenti interni (PCB, motore, batteria) per verificare l'accoppiamento e l'accumulo di tolleranze
- T1 findings and corrective actions:
- Inspect flash, sink marks, weld lines, fit, and surface texture against the drawing and sample criteria.
- Ask engineering to identify root cause before approving a design, process, or tooling change.
- Record corrective actions and re-trial timing in the project schedule; no single repair or turnaround applies to every case.
- Review the updated sample before approving the next stage.
- Richiedere la spedizione fisica dei campioni T1: Anche con le foto, la valutazione pratica rivela cose che una fotocamera non coglie. Qualità tattile, distribuzione del peso, sensazione dei pulsanti

Campione di Pre-Produzione (Prototipo Funzionale) e Test
Test del CampioneThe pre-production sample should represent the agreed design closely enough for review. Define tests, sample size, conditions, acceptance criteria, and any changes requiring reassessment.
- Functional sample testing:
- Battery runtime: Define sample, charge state, operating mode, load, and stop criteria. One condition does not establish runtime for every mode or battery.
- IPX7 immersion: Use applicable IEC 60529 conditions, commonly 1 m for 30 minutes for the relevant enclosure. Longer duration is not an IPX7 requirement; an air-pressure screen is not the water test.
- Test di caduta: Agree sample, height, surface, orientations, repetitions, and pass criteria in the project protocol.
- Brush-head attachment: Define sample, cycle count, and evaluation criteria in the product specification.
- Charging/cycle test: Specify charger, battery, cycle count, measurements, and acceptance criteria.
- Vibration measurement: Document instrument, measurement point, method, and metric; distinguish sonic vibration from ultrasonic frequency and rotational speed.
- Temperature test: Define product state, exposure duration, operating condition, and criteria; limited testing does not prove all-environment performance.
- Revisione del prototipo di confezione: Controllare i colori stampati della confezione retail (richiedere una prova Pantone accurata), la scansionabilità del codice a barre e l'adattamento della cartolina inserita
- User manual review: Check labeling and instructions against the requirements applicable to each destination market and product configuration.
Prima di approvare il campione di pre-produzione
Compare the production-representative sample and documented results against the agreed specifications and criteria. Determine whether changes require further testing or approval before production.
Conferma dell'ordine di acquisto e pianificazione della produzione
Avvio della produzione di massaAfter sample and commercial terms are approved, issue a purchase order and confirm the production slot. Define specifications, quantity, price, delivery terms, inspection criteria, and payment schedule in writing.
- Emettere un ordine di acquisto formale: Il vostro ordine di acquisto firmato deve specificare le quantità esatte per SKU, prezzo unitario, Incoterms, scadenza di consegna, specifiche di imballaggio e termini di pagamento
- Conferma del programma di produzione: La fabbrica fornisce un diagramma di Gantt o un programma di produzione che mostra la data di inizio, la data di completamento stimata e le tappe di controllo qualità
- Component procurement: Confirm availability and lead times for specified PCBs, batteries, motors, and materials with the supplier; update the project schedule if an item is not ready.
- Packaging production kickoff: Coordinate artwork approval, production quantity, and delivery timing with the packaging supplier and assembly schedule.
- Inspection planning: Agree the inspection scope, provider, sample plan, and timing with the supplier and inspector; availability varies.
Fase 3 — Produzione di massa (settimane 9–12)
Agree on status updates and records to be shared. Use documented progress, inspection results, and issue tracking; follow the supplier agreement and site rules.

Produzione attiva e controllo qualità in linea
ProduzioneDocument production checkpoints, test coverage, sample plans, limits, and failure handling against the approved specification.
- Inline quality checkpoints (document the agreed plan):
- Housing: check dimensions and visible defects against the approved specification and sampling plan.
- PCB: document test coverage and limits; describe a check as 100% only if each unit receives the stated test.
- Assembly: verify alignment and seals against the specification. An air-pressure screen is not an IEC 60529 water-ingress test.
- Final function: identify the functions tested per unit and how failures are recorded and handled.
- Packaging: verify SKU, labels, accessories, and carton data against the approved specification.
- Richiedere foto/video settimanali della produzione: Unità completate sulla linea, registrazioni delle ispezioni di controllo qualità e linea di imballaggio in funzione
- Monitorare l'avanzamento della produzione: For example, compare reported output with the production schedule and order quantity; investigate material variances early.
- If testing is required, confirm representative samples, scope, lab schedule, and production-change implications with the lab; timing is not guaranteed.
Bandiere rosse a metà produzione: agire immediatamente su queste
If the factory goes quiet without explanation, something is wrong. If they suddenly ask to substitute a component because of "stock issues," push back—get the original spec or a written explanation. If production pace falls significantly behind schedule with no clear reason, escalate. If a supplier requests payment ahead of an agreed milestone, compare the request with the contract and resolve any discrepancy in writing before payment.

Completamento della produzione e ispezione pre-spedizione
Controllo qualità e ispezionePre-shipment inspection can check goods against the agreed purchase order and acceptance plan. Define scope and process in advance; it does not guarantee every shipped unit.
- Ambito dell'ispezione pre-spedizione:
- Quantity: compare physical count with the PO and any tolerance expressly agreed in contract.
- Sampling: specify procedure, inspection level, sample size, defect classes, and acceptance/rejection numbers. AQL is a plan parameter, not measured defect rate; MIL-STD-1916 uses verification levels, not an AQL table.
- Workmanship: assess surface, color, assembly, and agreed criteria.
- Function: identify test functions, sample plan, and pass criteria.
- Packaging: verify carton markings, accessories, and barcodes against the approved specification.
- Carton drop testing: use the agreed protocol for height, orientations, surface, repetitions, and acceptance criteria.
- Choose an independent provider, buyer-appointed representative, or supplier records based on the agreed scope and evidence requirements. Fees and availability vary; confirm in writing.
- Document the nonconformity, corrective action, rework, and re-inspection criteria. Added time depends on the issue and agreed disposition.
- Prepare documents according to route, product, battery configuration, destination, and buyer requirements. Use a certificate of origin or conformity document only when applicable.
Criteri di superamento per l'ispezione pre-spedizione
Use the quantity, sampling plan, function checks, packaging, markings, and documents in the contract. If results miss criteria, document corrective action and verify closure before shipment.
Fase 4 — Spedizione e Sdoganamento (Settimane 13–16)
Shipping and customs timing depends on route, carrier, service, documents, battery configuration, port conditions, and clearance. Treat the week numbers as illustrative and confirm the current plan.

Ritiro Merce e Dogana di Esportazione (Lato Cina)
PartenzaThe forwarder coordinates pickup and export formalities. Clearance timing depends on the shipment and its documents; confirm cutoffs and required records for the chosen service.
- Sea freight planning examples:
- Shenzhen to Los Angeles: request a current route and service estimate.
- Shenzhen to Hamburg or Rotterdam: request a current route and service estimate.
- Shenzhen to Tokyo or Osaka: request a current route and service estimate.
- Shenzhen to Sydney: request a current route and service estimate.
- Air freight may suit samples or urgent shipments. Transit and cost depend on route, service, chargeable weight, battery acceptance, and current capacity; compare current quotes.
- Classification depends on product configuration, jurisdiction, origin, and import date. Treat HS 8509.80 only as a possible heading to investigate, not a final national tariff code or duty.
- Shipment document checklist (confirm what applies):
- Commercial invoice with accurate transaction value and required shipment information.
- Packing list with package count, weights, dimensions, and contents as required.
- Bill of Lading or Air Waybill for the selected service.
- Certificate of origin only if required by destination, buyer, or applicable procedure; confirm correct form and origin rules.
- Applicable conformity documentation for the product and destination.
- FCC documentation only when applicable to the product and import.
- Battery test summary and shipping information required for the battery design and shipment mode.
Critico: Conformità alla Spedizione di Batterie al Litio
For lithium-battery products, identify battery type, watt-hours, packing configuration, shipment mode, and applicable rules. Obtain the required UN 38.3 test summary and confirm declarations and labels for that shipment; air and sea rules differ.
In Transito e Preparazione Doganale all'Importazione
TransitoPrepare import paperwork before arrival. Confirm free time, storage or demurrage terms, and broker deadlines from current carrier and port information; charges vary.
- Share documents according to the broker’s agreed lead time. Pre-arrival review can identify gaps; no fixed number of days applies to every shipment.
- For applicable U.S. vessel shipments, determine whether ISF applies and submit required information within the regulatory timeframe before loading. ISF is not a general air-freight filing.
- For EU imports, confirm the economic operator and importer arrangements, applicable conformity documents, and customs registration requirements with the importer and broker. Keep these separate from the rules for Great Britain and Northern Ireland.
- Confirm the conformity route for Great Britain or Northern Ireland and the product. Great Britain recognizes CE alongside UKCA for many applicable products under current arrangements; Northern Ireland differs.
- Dazi all'importazione da preventivare:
- US: duty and additional tariffs depend on final classification, origin, product details, and import date. Check current official sources and obtain broker advice.
- EU: determine duty from the final classification, origin, and import date; do not rely on a generic percentage.
- UK: determine duty from the final commodity code, origin, and import date.
- Prepare fulfillment requirements before dispatch. For Amazon FBA, confirm current carton, labeling, prep, and shipment-plan requirements in Seller Central; these differ from standard third-party logistics.
Consegna, Ricezione e Avvio dell'Inventario
ArrivoLa merce viene sdoganata e consegnata al tuo magazzino o centro di evasione ordini. Il progetto OEM è completo. Ma il lavoro non è finito. La ricezione è un punto di controllo qualità che molti marchi saltano a loro danno.
- Reconcile carton count and visible condition, then inspect units under the receiving plan agreed for the order. Any percentage sample is project-specific, not universal.
- Aggiornamento del sistema di inventario: Registra numeri di lotto, date di produzione e codici batch. Questo è importante per richieste di garanzia e potenziali richiami.
- Amazon FBA receiving (if applicable): Reconcile delivered cartons and monitor receiving status against the shipment plan created before dispatch. Inventory availability depends on Amazon's processing.
- Fotografia e aggiornamento dell'inserzione: Se non hai già foto del prodotto, organizza immediatamente un servizio fotografico interno o in studio. Vuoi che le inserzioni siano attive entro pochi giorni dalla disponibilità dell'inventario.
- Analisi finale del progetto: Documenta cosa è andato bene, cosa ha causato ritardi e cosa faresti diversamente. Questo diventa la tua SOP di produzione per il prossimo ciclo produttivo.
Pronto per Avviare il Tuo Progetto di Spazzolino Elettrico OEM?
Share your project brief to discuss a quotation and schedule. Scope, MOQ, tooling, testing, sample terms, and current capacity depend on the product and written agreement.
Qual è la tua data di lancio prevista? Includila nel modulo: ti diremo se la tempistica è realistica.
6. Existing-Platform ODM Options
ODM may suit a project that fits an existing platform and available configuration. New tooling may still be needed for structural changes; branding, accessories, packaging, testing, and schedule depend on the agreed scope. Compare total cost, MOQ, rights, and timing with an OEM proposal.
Custom OEM: A project-specific design may involve engineering and structural tooling. Confirm timeline, tooling charges, MOQ, design scope, and intellectual-property rights in the written agreement.

Existing-platform ODM: An existing platform may reduce some development or tooling work if it fits the brief. Confirm customization limits, setup charges, MOQ, testing, schedule, and intellectual-property rights in the written agreement.
Illustrative ODM Milestones
The sequence below shows how work may progress on an existing platform; confirm sample, production, freight, and receiving dates for the actual project.
| Settimana | Attività | Azione chiave per te |
|---|---|---|
| Settimana 1 | Browse existing-platform options, if available, and request project-specific samples. | Review product fit, configuration, sample terms, MOQ, and schedule. |
| Settimana 2 | Ricevi i campioni; testa la funzionalità; conferma la selezione | Approva il modello del prodotto |
| Settimana 3 | Invia branding: logo, colori, design dell'imballaggio | Fornisci risorse complete del marchio |
| Settimana 4 | La fabbrica prepara il campione di pre-produzione personalizzato | Rivedi e approva il campione |
| Settimana 5 | Issue the purchase order and follow the written payment terms. | Emetti l'ordine di acquisto |
| Settimane 6–8 | Produzione di massa, controllo qualità in linea, imballaggio | Monitora i progressi, prenota l'ispezione pre-spedizione |
| Settimana 9 | Review inspection results and follow the agreed payment and shipping terms. | Approva l'ispezione, organizza il trasporto |
| Settimana 10 | Sdoganamento, consegna | Ricevi l'inventario, attiva le inserzioni |
Quando l'ODM batte l'OEM
ODM may suit a project that fits an existing platform. Compare MOQ, customization, tooling or setup charges, testing, schedule, IP terms, and total cost with an OEM proposal; confirm any trial quantity in writing.
Dove le tempistiche OEM si rompono effettivamente
The following factors can affect a project schedule; assess them against the supplier plan and current service estimates.

Mold revisions and design changes
Review design and tooling changes before fabrication. Record approval, cost, and schedule impact in the project plan.
Arretrati dei laboratori di certificazione — invisibili finché non sei bloccato
Laboratory availability varies by product, test scope, market, season, and provider. Confirm current availability and whether representative samples can be evaluated.
Capodanno cinese — l'interruzione che puoi vedere arrivare con 12 mesi di anticipo
Chinese New Year dates and supplier closures vary by year and factory. Check the official calendar and obtain planned closure and restart dates from each supplier; use a project-specific buffer.
Imballaggio e prodotto che arrivano in momenti diversi
Packaging may come from a separate supplier. Coordinate artwork, quantity, production, and delivery dates with the packaging supplier.
Cicli di revisione dei campioni — feedback che continua ad arrivare
Revision rounds can extend sample approval. Consolidate feedback in one document, rank issues, and confirm the schedule impact of each approved change.
Carenze di componenti — il problema della catena di approvvigionamento che emerge a metà produzione
Components such as PCBs and batteries can affect timing if supply is not confirmed. Ask the supplier to document availability and proposed alternatives; assess any substitution through change control. A second source may help where technically and contractually feasible.
Ritardi di spedizione e portuali — l'ultimo miglio che aggiunge settimane
Freight schedules vary with routing, capacity, port conditions, documents, and customs. Use current estimates and allow a project-specific buffer.
Keep milestones and decisions visible
Agree on a regular update cadence and document milestones, open issues, and decisions. Follow up on unexplained communication gaps and assess their effect on the project schedule.
Pianificazione a calendario inverso: Lavorare a ritroso dalla data di lancio
Reverse-calendar planning can clarify dependencies. Work backward from a target availability date using supplier, testing, production, freight, customs, and warehouse estimates confirmed for the project.

Esempio: Pianificazione per un lancio per le festività del Q4 su Amazon
Illustrative target only: confirm current event eligibility, FBA appointments, receiving requirements, and the actual transit plan; this is not an official deadline.
| Pietra miliare | Data obiettivo | Note |
|---|---|---|
| Prodotti ricevuti nel magazzino FBA | 1 ottobre | Allow for current FBA appointment, receiving, and processing times; these vary and are not a fixed 1–2-week guarantee. |
| Sdoganamento + consegna dell'ultimo miglio | 25 settembre | Illustrative only; confirm port, clearance, and last-mile timing for the route. |
| Spedizione da Shenzhen (trasporto marittimo) | 28 agosto | Illustrative port-to-port estimate only; confirm current route, service, and door-to-door timing with the forwarder. |
| Ispezione pre-spedizione superata | 21 agosto | Allow time for inspection and documents according to the agreed scope and route. |
| Produzione di massa completata | 14 agosto | Illustrative production window; confirm current capacity and schedule. |
| Purchase Order issued / payment milestone per contract | 17 luglio | Inizio della produzione di massa |
| Campione di pre-produzione approvato | 10 luglio | Allow for sample review and applicable testing; confirm scope and laboratory schedule. |
| Campioni dello stampo T1 ricevuti | 26 giugno | Review time depends on findings, corrective work, and approval. |
| Inizio fabbricazione dello stampo | 5 giugno | Illustrative tooling window; request a project-specific estimate. |
| Fabbrica selezionata, contratto firmato | 29 maggio | NDA, design dello stampo approvato |
| Inizio richiesta di preventivo (RFQ) | 22 maggio | Iniziare la ricerca della fabbrica qui |
Per un lancio Amazon FBA il 1 ottobre: Iniziare la ricerca della fabbrica entro il 22 maggio
May 22 to October 1 is 132 days, about 18 weeks and 6 days in this example. This is a planning window, not a promise; update dates as milestones are confirmed.
Se hai perso la finestra di maggio: compare a suitable existing-platform ODM option or revise the launch target. Actual timing and seasonal demand depend on the project and market.
Guida alla tempistica della stagione di punta

| Finestra di lancio target | Illustrative OEM Start Date | Illustrative ODM Start Date | Note |
|---|---|---|---|
| Gennaio (Capodanno) | 1 settembre | 15 ottobre | Check the official calendar and obtain supplier closure and restart dates for the relevant year. |
| Febbraio (San Valentino) | 15 ottobre | 1 dicembre | Illustrative note only; confirm the official holiday calendar and each supplier’s closure and restart dates. |
| Aprile (Primavera) | 1 dicembre | 15 gennaio | Confirm supplier availability and restart dates for the relevant year. |
| Luglio (Prime Day) | 1 marzo | 15 aprile | Illustrative example only; verify current supplier and logistics availability. |
| Ottobre (Pre-Festività) | 22 maggio | 15 luglio | Illustrative channel note; verify current market conditions. |
| Novembre (Black Friday) | 15 giugno | 1 agosto | Confirm current event-specific eligibility and submission dates; no universal October 15 cutoff is asserted. |
📚 Riferimenti

9. Domande frequenti
Ottieni una Tempistica OEM Personalizzata per il Tuo Progetto
Tell us your target launch date and product requirements. Our project team can discuss a project-specific schedule and applicable commercial terms.
Tip: Include your target launch date, destination market, and product requirements so the schedule discussion can account for project constraints.

Continua la Tua Ricerca OEM
- La guida completa alla produzione di spazzolini elettrici OEM/ODM (2026): Panoramica completa di costi, certificazioni, controllo qualità, selezione della fabbrica
- OEM vs ODM vs OBM: Quale Modello di Produzione è Giusto per il Tuo Marchio?: Quadro decisionale con confronti di costi reali
- Come Trovare un Produttore OEM in Cina: 6 Metodi Comprovati: Fiera di Canton, Alibaba, audit di fabbrica e due diligence
- CE, FCC, PSE e altro: la guida completa alle certificazioni per spazzolini elettrici: Ogni certificazione necessaria, per mercato
- Guida al branding Private Label: dal logo al lancio: Design del packaging, identità del marchio e strategia di lancio sul mercato
- Guida all'acquisto Water Flosser OEM/ODM: Vuoi espanderti a una linea di prodotti per l'igiene orale multi-prodotto? Inizia qui