Calendrier des brosses à dents électriques OEM : Guide du processus semaine par semaine (2026)
Project timelines depend on product scope, tooling, approvals, testing, supplier readiness, freight, customs, and destination. Use the calendar below as a planning example, then confirm milestones against the project and current availability.

Résumé : Calendrier de production des brosses à dents électriques OEM
- Standard OEM Timeline : 12–16 weeks (84–112 days) is an illustrative inquiry-to-delivery planning range, not a guaranteed lead time. Confirm the project schedule.
- An existing-platform ODM project may avoid some structural tooling if the model and configuration fit. MOQ, customization, setup charges, testing, and timing depend on the product and written terms.
- Principaux risques de retard : Schedule risks can include design changes, testing availability, supplier closures, component or packaging readiness, freight, and customs. Set project-specific buffers and confirm dates with the relevant providers.
- Payment and tooling milestones are negotiated contract terms. Specify deposits, balance triggers, tooling ownership, acceptance conditions, and nonconformity handling in the signed agreement.
Dans ce guide
- La chronologie complète en un coup d'œil
- Phase 1 : Enquête et sélection de l'usine (semaines 1-2)
- Phase 2 : Développement d'échantillons et de prototypes (semaines 3 à 8)
- Phase 3 : Production de masse (semaines 9 à 12)
- Phase 4 : Expédition et dédouanement (semaines 13 à 16)
- Existing-platform ODM options
- Principaux risques de retard et comment les prévenir
- Planification du calendrier inversé : Travaillez à l'envers à partir de votre date de lancement
- Questions fréquentes
1. Le calendrier complet en un coup d'œil
Avant de se plonger dans les semaines individuelles, voici le tableau complet. Connaître la forme générale du calendrier vous aidera à négocier avec les usines, à fixer des dates de lancement réalistes et à déterminer où le temps tampon est le plus important.

🏭 A propos du fabricant : Relish Technology
Relish Technology has manufactured oral-care products since 2012. Its operations in Shenzhen and Huizhou total 20,000 m². Share the product configuration, target market, order scope, and schedule to discuss relevant manufacturing options and product-specific documentation.
En savoir plus → · Études de cas de clients → · Voir les certifications →
OEM Electric Toothbrush: Illustrative 16-Week Timeline (Visual Overview)
| Phase | Semaines | Activités principales | Vos points de décision |
|---|---|---|---|
| 1. Enquête et sélection | 1-2 | Appel d'offres, comparaison des devis, signature de l'accord de confidentialité, présélection des usines | Choisir l'usine, confirmer les spécifications |
| 2. Création de moules | 3-6 | Revue d'ingénierie, fabrication du moule, premier essai du moule | Approuver la conception du moule, payer le dépôt d'outillage |
| 3. Prototype et approbation | 7-8 | Premiers échantillons, tests, révisions, approbation de la préproduction | Approuver les échantillons, signer le bon de commande |
| 4. Production de masse | 9-12 | Production deposit, inline checks, packaging, and pre-shipment inspection: schedule and payment terms are project-specific and contractual. | Review inspection results and follow the payment terms agreed in the contract. |
| 5. Expédition et dédouanement | 13-16 | Fret maritime et aérien, courtier en douane, livraison du dernier kilomètre | Confirmation de la réception, enregistrement de l'inventaire |
Un numéro à retenir
Use the 16-week calendar as an example, then build a project-specific schedule. Add time for design changes, sample review, testing, transport, and clearance after confirming requirements with each supplier or service provider.
2. Phase 1 - Enquête et sélection de l'usine (semaines 1-2)
Early supplier evaluation helps clarify product scope, documentation, commercial terms, and schedule assumptions before tooling or production begins.

Préparation de l'appel d'offres et sensibilisation de plusieurs usines
Demande de renseignementsCommencez la première semaine en rédigeant un Demande de devis (RFQ) et l'envoyer à 4-6 usines simultanément. La qualité de votre appel d'offres détermine la qualité des devis que vous recevrez en retour. Les demandes vagues donnent lieu à des réponses vagues et à des prix gonflés qui ne sont évidents que plus tard.
- Define product specifications: Drive technology and specified motion metric, battery voltage and capacity/Wh, applicable ingress-protection target, handle dimensions, brush-head type, charging method, and operating modes.
- Fixez vos quantités cibles : Indiquez la quantité de votre commande initiale et le volume annuel prévu. Les usines fixent des prix différents pour 500 et 5 000 unités.
- List destination-market compliance requirements: identify applicable product rules and evidence for the model and configuration; confirm testing and documentation with the laboratory or qualified adviser.
- Spécifier les exigences en matière d'emballage : Dimensions de la boîte de vente au détail, carte d'insertion, carton principal, exigences en matière d'étiquetage Amazon-ready
- Identifier 4 à 6 usines candidates : Utilisez les annuaires de Canton Fair, le filtre Alibaba Gold Supplier, Made-in-China.com, ou des références directes.
Un appel d'offres complet couvre les huit points suivants
Le nom du produit et une description d'une à deux lignes. Une fiche technique indiquant les dimensions, les matériaux et les objectifs de performance. Le(s) marché(s) cible(s) et les certifications requises. La quantité de la commande initiale et une prévision de volume sur 12 mois. Les spécifications d'emballage pour la vente au détail et le carton principal. Quantité d'échantillons et délais de livraison. La fourchette de prix FOB visée - cette information est facultative, mais elle permet d'écarter les usines qui ne sont pas compétitives dans votre fourchette. Conditions de paiement prévues.
Évaluation du devis et sélection de l'usine
La sélectionCompare quotations on identical specifications, quantity, Incoterms, testing, packaging, and documentation. Assess total landed cost and assumptions; price alone does not establish supplier quality or future rework cost.
- Comparez les devis sur la même base : Confirmer que tous les devis utilisent les mêmes incoterms (généralement FOB Shenzhen), incluent les mêmes certifications et couvrent des spécifications d'emballage identiques.
- Verify the supplier: Check its business registration and any claimed ISO 9001 certificate. For comparable products, request model-specific test reports and conformity documents relevant to your target market. CE is a conformity mark; FCC requirements depend on the product configuration.
- Évaluer la vitesse de communication : Track response times during evaluation and agree on communication expectations and escalation contacts before production.
- Demander le profil de l'usine : Combien de lignes de production ? Capacité annuelle ? Principaux clients actuels (sous couvert d'anonymat) ? Ont-ils déjà exporté vers votre marché cible ?
- Shortlist suppliers for further review. If needed, commission a scoped factory audit and obtain a current quotation from the provider.
À quoi ressemble une usine fiable
A supplier should explain its capabilities, identify open technical questions, provide current documentation for comparable products, and agree on a practical communication and review process. Verify claims against the project scope.
Éloignez-vous si vous voyez ceci
Investigate inconsistent quotations, unclear documentation, or pressure to skip written terms. Compare like-for-like costs and seek clarification; no single signal proves fraud.
3. Phase 2 - Développement d'échantillons et de prototypes (semaines 3 à 8)
Sample development may take several weeks and require review rounds. Consolidate feedback, document approved changes, and evaluate new requirements against the schedule.

Examen technique et confirmation de la conception du moule
Coup d'envoi de l'outillageAfter scope and commercial terms are agreed, engineering reviews design, tooling, materials, assembly, and available processes. The number of questions and response time depend on the project.
- DFM review: Ask engineering to identify design, tooling, assembly, and process questions and document any proposed changes.
- Review proposed CAD and tooling designs before authorizing fabrication. Changes after work begins may affect engineering, time, and cost; define approval and tooling ownership in writing.
- Confirmation des matériaux : Confirmer le matériau du manche (ABS / PC / mélange ABS+PC), le matériau des poils (qualité nylon / DuPont Tynex) et les spécifications du surmoulage TPE/caoutchouc.
- Document the relevant vibration or brush-head movement metric and test method; distinguish VPM, Hz, and rotational speed. Do not call sonic operation ultrasonic without supporting frequency data.
- Tooling cost and payment timing depend on design and contract. Agree amount, ownership, acceptance milestone, and payment triggers in writing.
Fabrication de moules (usinage CNC)
OutillageDuring mold fabrication, request updates at agreed milestones. Toolmaking requires inspection and adjustment; the appropriate correction depends on the issue and engineering assessment.
- Tooling lead time and durability depend on design, material, process, workload, production conditions, and maintenance. Obtain a project-specific estimate.
- Demander des photos de l'état d'avancement des travaux : Demandez des photos d'usinage CNC à l'achèvement des 50% et 100%
- Tâches parallèles pendant cette attente :
- Finaliser le logo de la marque et la palette de couleurs pour la texturation des moules
- Projet de conception de l'emballage de vente au détail pour examen par l'usine
- Ask your testing lab to review the rules and test scope for the intended product and destination markets.
- Prepare importer-of-record arrangements if required for the destination and transaction.
- Tool life depends on grade, heat treatment, mold design, resin, production conditions, and maintenance; quoted shot counts are not universal guarantees.
Ne perdez pas les semaines 4 et 5 à attendre
Use the mold fabrication period to finalize packaging design and send it to the factory for a mockup. Register barcodes (EAN/UPC) for each SKU early enough to support listing and packaging preparation. Prepare listing copy, warehouse arrangements, and draft manuals while tooling is underway. Review regulatory requirements with the laboratory early; product testing and final approvals may need representative samples.
Premier essai sur les moisissures et échantillons T1
Premiers coups de feuA first mold trial (often called T1) evaluates molded parts and fit. It may identify dimensional, surface, or assembly issues and is not necessarily a complete functional product.
- Contrôle dimensionnel T1 : L'usine mesure les dimensions critiques par rapport aux dessins approuvés à l'aide d'une MMT (machine à mesurer les coordonnées) ou d'un pied à coulisse.
- Examen de l'état de surface : Vérifier la texture, le niveau de brillance, la visibilité du plan de joint, ainsi que les éventuelles marques d'enfoncement ou lignes de soudure.
- Procès de l'Assemblée : Les moitiés du boîtier sont assemblées avec les composants internes (circuit imprimé, moteur, batterie) pour vérifier l'ajustement et l'empilement des tolérances.
- T1 findings and corrective actions:
- Inspect flash, sink marks, weld lines, fit, and surface texture against the drawing and sample criteria.
- Ask engineering to identify root cause before approving a design, process, or tooling change.
- Record corrective actions and re-trial timing in the project schedule; no single repair or turnaround applies to every case.
- Review the updated sample before approving the next stage.
- Demande d'échantillons T1 physiquement expédiés : Même avec des photos, l'évaluation pratique révèle des éléments qui échappent à l'appareil photo. Qualité tactile, répartition du poids, sensation des boutons

Échantillon de préproduction (prototype fonctionnel) et essais
Test d'échantillonsThe pre-production sample should represent the agreed design closely enough for review. Define tests, sample size, conditions, acceptance criteria, and any changes requiring reassessment.
- Functional sample testing:
- Battery runtime: Define sample, charge state, operating mode, load, and stop criteria. One condition does not establish runtime for every mode or battery.
- IPX7 immersion: Use applicable IEC 60529 conditions, commonly 1 m for 30 minutes for the relevant enclosure. Longer duration is not an IPX7 requirement; an air-pressure screen is not the water test.
- Test de chute : Agree sample, height, surface, orientations, repetitions, and pass criteria in the project protocol.
- Brush-head attachment: Define sample, cycle count, and evaluation criteria in the product specification.
- Charging/cycle test: Specify charger, battery, cycle count, measurements, and acceptance criteria.
- Vibration measurement: Document instrument, measurement point, method, and metric; distinguish sonic vibration from ultrasonic frequency and rotational speed.
- Temperature test: Define product state, exposure duration, operating condition, and criteria; limited testing does not prove all-environment performance.
- Examen du prototype d'emballage : Vérifier les couleurs d'impression de la boîte de vente au détail (demander une épreuve Pantone précise), la lisibilité du code-barres et l'ajustement de la carte d'insertion.
- User manual review: Check labeling and instructions against the requirements applicable to each destination market and product configuration.
Avant d'approuver l'échantillon de préproduction
Compare the production-representative sample and documented results against the agreed specifications and criteria. Determine whether changes require further testing or approval before production.
Confirmation du bon de commande et programmation de la production
Coup d'envoi de la production de masseAfter sample and commercial terms are approved, issue a purchase order and confirm the production slot. Define specifications, quantity, price, delivery terms, inspection criteria, and payment schedule in writing.
- Délivrer un PO formel : Le bon de commande signé doit préciser les quantités exactes par UGS, le prix unitaire, les Incoterms, le délai de livraison, les spécifications d'emballage et les conditions de paiement.
- Confirmation du calendrier de production : L'usine fournit un diagramme de Gantt ou un calendrier de production indiquant la date de début, l'achèvement prévu et les étapes du contrôle qualité.
- Component procurement: Confirm availability and lead times for specified PCBs, batteries, motors, and materials with the supplier; update the project schedule if an item is not ready.
- Packaging production kickoff: Coordinate artwork approval, production quantity, and delivery timing with the packaging supplier and assembly schedule.
- Inspection planning: Agree the inspection scope, provider, sample plan, and timing with the supplier and inspector; availability varies.
4. Phase 3 - Production de masse (semaines 9 à 12)
Agree on status updates and records to be shared. Use documented progress, inspection results, and issue tracking; follow the supplier agreement and site rules.

Production active et contrôle de qualité en ligne
ProductionDocument production checkpoints, test coverage, sample plans, limits, and failure handling against the approved specification.
- Inline quality checkpoints (document the agreed plan):
- Housing: check dimensions and visible defects against the approved specification and sampling plan.
- PCB: document test coverage and limits; describe a check as 100% only if each unit receives the stated test.
- Assembly: verify alignment and seals against the specification. An air-pressure screen is not an IEC 60529 water-ingress test.
- Final function: identify the functions tested per unit and how failures are recorded and handled.
- Packaging: verify SKU, labels, accessories, and carton data against the approved specification.
- Demander des photos/vidéos hebdomadaires de la production : Unités terminées sur la ligne, registres d'inspection CQ et ligne d'emballage en fonctionnement
- Suivre l'évolution de la production : For example, compare reported output with the production schedule and order quantity; investigate material variances early.
- If testing is required, confirm representative samples, scope, lab schedule, and production-change implications with the lab; timing is not guaranteed.
Signaux d'alerte en milieu de production : agissez immédiatement
If the factory goes quiet without explanation, something is wrong. If they suddenly ask to substitute a component because of "stock issues," push back—get the original spec or a written explanation. If production pace falls significantly behind schedule with no clear reason, escalate. If a supplier requests payment ahead of an agreed milestone, compare the request with the contract and resolve any discrepancy in writing before payment.

Achèvement de la production et inspection avant expédition
Contrôle de qualité et inspectionPre-shipment inspection can check goods against the agreed purchase order and acceptance plan. Define scope and process in advance; it does not guarantee every shipped unit.
- Champ d'application de l'inspection avant expédition :
- Quantity: compare physical count with the PO and any tolerance expressly agreed in contract.
- Sampling: specify procedure, inspection level, sample size, defect classes, and acceptance/rejection numbers. AQL is a plan parameter, not measured defect rate; MIL-STD-1916 uses verification levels, not an AQL table.
- Workmanship: assess surface, color, assembly, and agreed criteria.
- Function: identify test functions, sample plan, and pass criteria.
- Packaging: verify carton markings, accessories, and barcodes against the approved specification.
- Carton drop testing: use the agreed protocol for height, orientations, surface, repetitions, and acceptance criteria.
- Choose an independent provider, buyer-appointed representative, or supplier records based on the agreed scope and evidence requirements. Fees and availability vary; confirm in writing.
- Document the nonconformity, corrective action, rework, and re-inspection criteria. Added time depends on the issue and agreed disposition.
- Prepare documents according to route, product, battery configuration, destination, and buyer requirements. Use a certificate of origin or conformity document only when applicable.
Critères de réussite pour l'inspection avant expédition
Use the quantity, sampling plan, function checks, packaging, markings, and documents in the contract. If results miss criteria, document corrective action and verify closure before shipment.
5. Phase 4 - Expédition et dédouanement (semaines 13 à 16)
Shipping and customs timing depends on route, carrier, service, documents, battery configuration, port conditions, and clearance. Treat the week numbers as illustrative and confirm the current plan.

Enlèvement du fret et douanes à l'exportation (côté chinois)
DépartThe forwarder coordinates pickup and export formalities. Clearance timing depends on the shipment and its documents; confirm cutoffs and required records for the chosen service.
- Sea freight planning examples:
- Shenzhen to Los Angeles: request a current route and service estimate.
- Shenzhen to Hamburg or Rotterdam: request a current route and service estimate.
- Shenzhen to Tokyo or Osaka: request a current route and service estimate.
- Shenzhen to Sydney: request a current route and service estimate.
- Air freight may suit samples or urgent shipments. Transit and cost depend on route, service, chargeable weight, battery acceptance, and current capacity; compare current quotes.
- Classification depends on product configuration, jurisdiction, origin, and import date. Treat HS 8509.80 only as a possible heading to investigate, not a final national tariff code or duty.
- Shipment document checklist (confirm what applies):
- Commercial invoice with accurate transaction value and required shipment information.
- Packing list with package count, weights, dimensions, and contents as required.
- Bill of Lading or Air Waybill for the selected service.
- Certificate of origin only if required by destination, buyer, or applicable procedure; confirm correct form and origin rules.
- Applicable conformity documentation for the product and destination.
- FCC documentation only when applicable to the product and import.
- Battery test summary and shipping information required for the battery design and shipment mode.
Critique : Conformité de l'expédition des piles au lithium
For lithium-battery products, identify battery type, watt-hours, packing configuration, shipment mode, and applicable rules. Obtain the required UN 38.3 test summary and confirm declarations and labels for that shipment; air and sea rules differ.
Préparation des douanes en transit et à l'importation
TransitPrepare import paperwork before arrival. Confirm free time, storage or demurrage terms, and broker deadlines from current carrier and port information; charges vary.
- Share documents according to the broker’s agreed lead time. Pre-arrival review can identify gaps; no fixed number of days applies to every shipment.
- For applicable U.S. vessel shipments, determine whether ISF applies and submit required information within the regulatory timeframe before loading. ISF is not a general air-freight filing.
- For EU imports, confirm the economic operator and importer arrangements, applicable conformity documents, and customs registration requirements with the importer and broker. Keep these separate from the rules for Great Britain and Northern Ireland.
- Confirm the conformity route for Great Britain or Northern Ireland and the product. Great Britain recognizes CE alongside UKCA for many applicable products under current arrangements; Northern Ireland differs.
- Droits à l'importation à budgétiser :
- US: duty and additional tariffs depend on final classification, origin, product details, and import date. Check current official sources and obtain broker advice.
- EU: determine duty from the final classification, origin, and import date; do not rely on a generic percentage.
- UK: determine duty from the final commodity code, origin, and import date.
- Prepare fulfillment requirements before dispatch. For Amazon FBA, confirm current carton, labeling, prep, and shipment-plan requirements in Seller Central; these differ from standard third-party logistics.
Livraison, réception et mise en service de l'inventaire
ArrivéeLa cargaison est dédouanée et livrée à votre entrepôt ou à votre centre de traitement des commandes. Le projet OEM est terminé. Mais le travail n'est pas terminé. La réception est un point de contrôle de la qualité que de nombreuses marques négligent à leur détriment.
- Reconcile carton count and visible condition, then inspect units under the receiving plan agreed for the order. Any percentage sample is project-specific, not universal.
- Mise à jour du système d'inventaire : Enregistrez les numéros de lot, les dates de production et les codes de lot. Ces éléments sont importants pour les réclamations au titre de la garantie et les rappels éventuels
- Amazon FBA receiving (if applicable): Reconcile delivered cartons and monitor receiving status against the shipment plan created before dispatch. Inventory availability depends on Amazon's processing.
- Photographie et mise à jour des listes : Si vous ne disposez pas encore de photographies de produits, organisez immédiatement une prise de vue en interne ou en studio. Vous voulez que les listes soient en ligne dans les jours qui suivent la mise à disposition de l'inventaire
- Débriefing du projet : Documentez ce qui s'est bien passé, ce qui a causé des retards et ce que vous feriez différemment. Ce document devient le mode opératoire normalisé de la fabrication pour le prochain cycle de production.
Prêt à lancer votre projet de brosse à dents électrique OEM ?
Share your project brief to discuss a quotation and schedule. Scope, MOQ, tooling, testing, sample terms, and current capacity depend on the product and written agreement.
Quelle est votre date de lancement ? Indiquez-la dans le formulaire : nous vous dirons si le calendrier est réaliste.
6. Existing-Platform ODM Options
ODM may suit a project that fits an existing platform and available configuration. New tooling may still be needed for structural changes; branding, accessories, packaging, testing, and schedule depend on the agreed scope. Compare total cost, MOQ, rights, and timing with an OEM proposal.
Custom OEM: A project-specific design may involve engineering and structural tooling. Confirm timeline, tooling charges, MOQ, design scope, and intellectual-property rights in the written agreement.

Existing-platform ODM: An existing platform may reduce some development or tooling work if it fits the brief. Confirm customization limits, setup charges, MOQ, testing, schedule, and intellectual-property rights in the written agreement.
Illustrative ODM Milestones
The sequence below shows how work may progress on an existing platform; confirm sample, production, freight, and receiving dates for the actual project.
| Semaine | Activité | Action clé pour vous |
|---|---|---|
| Semaine 1 | Browse existing-platform options, if available, and request project-specific samples. | Review product fit, configuration, sample terms, MOQ, and schedule. |
| Semaine 2 | Recevoir des unités d'échantillonnage ; tester la fonctionnalité ; confirmer la sélection | Approuver le modèle de produit |
| Semaine 3 | Soumettre l'image de marque : logo, couleurs, conception de l'emballage | Fournir des actifs de marque complets |
| Semaine 4 | L'usine prépare des échantillons de pré-production personnalisés | Examiner et approuver l'échantillon |
| Semaine 5 | Issue the purchase order and follow the written payment terms. | PO d'émission |
| Semaines 6-8 | Production de masse, contrôle de qualité en ligne, emballage | Suivre les progrès, comptabiliser les IAE |
| Semaine 9 | Review inspection results and follow the agreed payment and shipping terms. | Approuver l'inspection, organiser le transport |
| Semaine 10 | Dédouanement, livraison | Recevoir l'inventaire, activer les listes |
Quand l'ODM bat l'OEM
ODM may suit a project that fits an existing platform. Compare MOQ, customization, tooling or setup charges, testing, schedule, IP terms, and total cost with an OEM proposal; confirm any trial quantity in writing.
7. Les cas où les délais des équipementiers ne sont pas respectés
The following factors can affect a project schedule; assess them against the supplier plan and current service estimates.

Mold revisions and design changes
Review design and tooling changes before fabrication. Record approval, cost, and schedule impact in the project plan.
Les retards dans les laboratoires de certification - invisibles jusqu'à ce que vous soyez bloqués
Laboratory availability varies by product, test scope, market, season, and provider. Confirm current availability and whether representative samples can be evaluated.
Nouvel an chinois : les perturbations que l'on peut prévoir 12 mois à l'avance
Chinese New Year dates and supplier closures vary by year and factory. Check the official calendar and obtain planned closure and restart dates from each supplier; use a project-specific buffer.
Emballage et produit arrivant à des moments différents
Packaging may come from a separate supplier. Coordinate artwork, quantity, production, and delivery dates with the packaging supplier.
Exemples de boucles de révision - un retour d'information permanent
Revision rounds can extend sample approval. Consolidate feedback in one document, rank issues, and confirm the schedule impact of each approved change.
Pénuries de composants - le problème de la chaîne d'approvisionnement qui apparaît à mi-production
Components such as PCBs and batteries can affect timing if supply is not confirmed. Ask the supplier to document availability and proposed alternatives; assess any substitution through change control. A second source may help where technically and contractually feasible.
Transport maritime et retards portuaires - le dernier kilomètre qui fait perdre des semaines
Freight schedules vary with routing, capacity, port conditions, documents, and customs. Use current estimates and allow a project-specific buffer.
Keep milestones and decisions visible
Agree on a regular update cadence and document milestones, open issues, and decisions. Follow up on unexplained communication gaps and assess their effect on the project schedule.
8. Planification à rebours du calendrier : Travaillez à l'envers à partir de votre date de lancement
Reverse-calendar planning can clarify dependencies. Work backward from a target availability date using supplier, testing, production, freight, customs, and warehouse estimates confirmed for the project.

Exemple : Planification du lancement d'Amazon au quatrième trimestre de la saison des fêtes
Illustrative target only: confirm current event eligibility, FBA appointments, receiving requirements, and the actual transit plan; this is not an official deadline.
| Jalon | Date cible | Notes |
|---|---|---|
| Produits reçus dans l'entrepôt FBA | 1er octobre | Allow for current FBA appointment, receiving, and processing times; these vary and are not a fixed 1–2-week guarantee. |
| Dédouanement + livraison du dernier kilomètre | 25 septembre | Illustrative only; confirm port, clearance, and last-mile timing for the route. |
| Expédition depuis Shenzhen (fret maritime) | 28 août | Illustrative port-to-port estimate only; confirm current route, service, and door-to-door timing with the forwarder. |
| Inspection avant expédition réussie | 21 août | Allow time for inspection and documents according to the agreed scope and route. |
| Production de masse terminée | 14 août | Illustrative production window; confirm current capacity and schedule. |
| Purchase Order issued / payment milestone per contract | 17 juillet | Début de la production en série |
| Approbation de l'échantillon de pré-production | 10 juillet | Allow for sample review and applicable testing; confirm scope and laboratory schedule. |
| Réception d'échantillons de moules T1 | 26 juin | Review time depends on findings, corrective work, and approval. |
| Début de la fabrication du moule | 5 juin | Illustrative tooling window; request a project-specific estimate. |
| Usine sélectionnée, contrat signé | 29 mai | NDA, approbation de la conception du moule |
| Début de la diffusion de l'appel d'offres | 22 mai | Commencez votre recherche d'usine ici |
Pour un lancement d'Amazon FBA le 1er octobre : Commencez votre recherche d'usine d'ici le 22 mai
May 22 to October 1 is 132 days, about 18 weeks and 6 days in this example. This is a planning window, not a promise; update dates as milestones are confirmed.
Si vous avez manqué la fenêtre de mai : compare a suitable existing-platform ODM option or revise the launch target. Actual timing and seasonal demand depend on the project and market.
Guide des périodes de haute saison

| Fenêtre de lancement de l'objectif | Illustrative OEM Start Date | Illustrative ODM Start Date | Notes |
|---|---|---|---|
| Janvier (Nouvel An) | 1er septembre | 15 octobre | Check the official calendar and obtain supplier closure and restart dates for the relevant year. |
| Février (Saint-Valentin) | 15 octobre | 1er décembre | Illustrative note only; confirm the official holiday calendar and each supplier’s closure and restart dates. |
| Avril (printemps) | 1er décembre | 15 janvier | Confirm supplier availability and restart dates for the relevant year. |
| Juillet (Prime Day) | 1er mars | 15 avril | Illustrative example only; verify current supplier and logistics availability. |
| Octobre (avant les vacances) | 22 mai | 15 juillet | Illustrative channel note; verify current market conditions. |
| Novembre (vendredi noir) | 15 juin | 1er août | Confirm current event-specific eligibility and submission dates; no universal October 15 cutoff is asserted. |
📚 Références

9. Questions fréquentes
Obtenez un calendrier OEM personnalisé pour votre projet
Tell us your target launch date and product requirements. Our project team can discuss a project-specific schedule and applicable commercial terms.
Tip: Include your target launch date, destination market, and product requirements so the schedule discussion can account for project constraints.

Poursuivez vos recherches sur les OEM
- Le guide complet de la fabrication de brosses à dents électriques OEM/ODM (2026): Aperçu complet des coûts, des certifications, du contrôle de la qualité, de la sélection des usines
- OEM vs ODM vs OBM : Quel modèle de fabrication convient le mieux à votre marque ?: Cadre décisionnel avec comparaison des coûts réels
- Comment trouver un fabricant OEM en Chine : 6 méthodes éprouvées: Foire de Canton, Alibaba, audits d'usine et diligence raisonnable
- CE, FCC, PSE et autres : Le guide complet de certification des brosses à dents électriques: Toutes les certifications dont vous avez besoin, par marché
- Guide de la marque privée : Du logo au lancement: Conception de l'emballage, identité de la marque et stratégie de lancement sur le marché
- Guide de l'acheteur OEM/ODM pour le purificateur d'eau: Développement d'une ligne de soins bucco-dentaires multi-produits ? Commencez ici